Construction Updates

Anderson Rd to 162 Ave SW

May 2018

Driving Piling at 162 Avenue
May 2, 2018
KGL Constructors will be driving piling for the new bridge at 162 Avenue, which will span the future northbound and southbound lanes of the Southwest Calgary Ring Road.
Advisory

 

Pathway Realignments near Cedarbrae and Woodbine
May 1, 2018
KGL is starting earthworks near the communities of Cedarbrae and Woodbine for the construction of new portions of pedestrian pathway.
Advisory

 

January 2018

Driving Piling near 130 Avenue/Buffalo Run Boulevard
January 3, 2018
KGL Constructors will be driving piling for a new bridge near the intersection of 37 Street S.W. and 130 Avenue / Buffalo Run Boulevard.
Advisory

 

November 2017

Driving Piling near Fish Creek Boulevard
November 22, 2017
KGL Constructors will be driving piling south of 146 Avenue and Fish Creek Boulevard S.W. for a new a bridge that will span the northbound and southbound lanes of the Southwest Calgary Ring Road.
Advisory

 

October 2017

Installation of Water and Sanitary Lines near 37 Street S.W.
October 20, 2017
KGL Constructors will be installing water and sanitary lines from an area near Woodbrook Road S.W. to the Tsuut’ina Nation administration office (Chief Joseph Big Plume Building).
Advisory

 

September 2017

Pathway Realignments near Cedarbrae and Woodbine
September 21, 2017
KGL Constructors is starting earthworks near the communities of Cedarbrae and Woodbine for the construction of new portions of pedestrian pathway.
Advisory

 

August 2017

Pile Driving near Fish Creek
August 1, 2017
KGL Constructors will be driving piling in the Transportation Utility Corridor in preparation for the new bridge that will be built across Fish Creek.
Advisory

 

June 2017

Change of Access to Tsuut’ina Nation
June 28, 2017
The opening of the new Buffalo Run Boulevard on July 1 and the closure of existing access on Bullhead Road on August 1.
Notice

 

May 2017

Relocation of Water Main at Fish Creek Boulevard S.W.
May 5, 2017
KGL Constructors will be relocating a water main near the intersection of 37 Street S.W., 146 Avenue and Fish Creek Boulevard S.W.
Advisory

 

February 2017

Start of Fish Creek Realignment
February 28, 2017
KGL will be realigning a portion of Fish Creek near future bridge structures. River realignment is a common engineering process that creates a new, permanent water channel. This will allow for the construction of the SWCRR bridges, while minimizing impact to the Fish Creek’s habitat by providing a bioengineered channel comparable to the river’s original path.
Advisory

 

ENMAX Utility Relocation
February 2017
ENMAX Power is constructing a new 138 kV transmission line in the west boundary of the Transportation Utility Corridor that will replace existing transmission infrastructure.
Newsletter – November 2016
Website

 

ENMAX Distribution Project
February 2017
ENMAX is continuing construction on the electrical distribution system north of Anderson Road SW to 146 Avenue S.W.
Newsletter – December 2016
Website

 

November 2016

KGL Office, Parking Lot & Equipment Yard
November 30, 2016
As preliminary construction continues for the Southwest Calgary Ring Road, KGL Constructors is building a new project site office, parking lot and equipment yard. This will be located within the transportation / utility corridor (TUC), adjacent to Bullhead Road and just north of the Tsuut’ina Nation Administration Building.
Advisory