Construction Updates

162 Ave SW to Macleod Trail SE

May 2017

Permanent closure of 24 Street S.W.
May 3, 2017
Traffic Advisory
Closure Notice

 

April 2017

Pile Driving at the Macleod Trail Interchange
April 24, 2017
Advisory

 

March 2017

Parking area at the intersection of Highway 22X and 37 Street S.W.
March 15, 2017
Closure Notice

 

January 2017

Earthworks and Excavation adjacent to Bridlewood
January 23, 2017
KGL Constructors will start working in the Transportation Utility Corridor (TUC) west of the community of Bridlewood. Activities include earthworks, an excavation, crushing operations and an asphalt processing plant.